One of its projects: Peninsula Four. This view was drawn for the developer.
Select Group projects, Dubai
This page covers 8 projects with 4,764 homes, as of 22 Oct 2026. Of these projects, 6 are finished and 2 are under construction.
Its registered name is Select Global Development L.L.C. This is not its full portfolio. Compare prices below. You can also track build progress.
Talk to Select Group- Finished projects
- 6
- Register to 22 Oct 2026
- Under construction
- 2
- 0% average completion
- Registered sales
- 930
- Across registered projects
Compare registered sales across projects
Compare prices at buildings linked to these projects by name.
| Peninsula Four | Business Bay | 2,520 | 214 | 76.0% | |
| Peninsula Three | Business Bay | 2,654 | 167 | 18.0% | |
| Artistry One Residences | Dubai International Financial Center | 3,139 | 151 | 100.0% | |
| The Edge | Business Bay | 2,442 | 125 | 100.0% | |
| Peninsula Two | Business Bay | 2,580 | 78 | 58.0% | |
| Peninsula One | Business Bay | 2,784 | 76 | 0.0% | |
| Artistry Two Residences | Dubai International Financial Center | 3,181 | 61 | 100.0% | |
| Peninsula Five | Business Bay | 2,621 | 17 | 0.0% |
Source: Land Department open data. Buildings need at least ten sales in the twelve months to 5 Oct 2026. Medians describe the sold mix of homes; they are not a same-size price ranking or asking-price quote. Projects without a building name match or an adequate recent sample are omitted from this comparison. A name match alone does not confirm project identity. Confirm the DLD project and unit before relying on a match. Their register records remain below. Compare the home-size table on each building page before choosing a unit.
Get advice on a Select Group home
Tell us what you need. With your consent, we share your request with the developer or agent for Select Group, who may contact you about it.
Thanks, the details are added to your request.
Under construction
Compare the recorded progress and completion dates for Select Group projects still being built.
Project register details
| Project | Community | Homes | Complete | Registered completion | Escrow bank | Median AED per sq ft |
|---|---|---|---|---|---|---|
| Artistry One Residences | Business Park | 232 | 0% | 9 Feb 2029 | Emirates Nbd Bank (P.J.S.C) | 3,139 |
| Artistry Two Residences | Business Park | 235 | 0% | 9 Feb 2029 | Emirates Nbd Bank (P.J.S.C) | 3,181 |
Source: the Land Department's project register, 22 Oct 2026. The table shows the recorded status and dates for these projects.
Finished projects
The register records below show the start and completion dates for finished Select Group projects.
Project register details
| Project | Community | Homes | Started | Completed | Build time | Median AED per sq ft |
|---|---|---|---|---|---|---|
| The Edge | Business Bay | 1,030 | 9 Jun 2023 | 11 Oct 2026 | 40 months | 2,442 |
| Peninsula Four | Business Bay | 1,038 | 1 Oct 2022 | 1 Feb 2026 | 40 months | 2,523 |
| Peninsula Three | Business Bay | 859 | 1 Jun 2022 | 1 Jun 2025 | 36 months | 2,654 |
| Peninsula Five | Business Bay | 383 | 15 Jan 2022 | 15 Dec 2024 | 35 months | 2,649 |
| Peninsula Two | Business Bay | 462 | 1 Nov 2021 | 1 Sept 2024 | 34 months | 2,585 |
| Peninsula One | Business Bay | 525 | 1 Aug 2021 | 1 Apr 2024 | 32 months | 2,793 |
Source: the Land Department's project register, 22 Oct 2026. The table shows the recorded start and finish dates.
Registered sales at matched project buildings
These home sales are for buildings linked to projects in the register. Each row shows the sale period.
| Business Bay | Finished | 214 | 12 months | 2,520 | 76.0% | Studio: 76 sales, median 1,287,500 AED; 1 bedroom: 99 sales, median 2,180,000 AED; 2 bedrooms: 25 sales, median 3,570,000 AED; 3 bedrooms: 12 sales, median 4,950,000 AED | |
| Business Bay | Finished | 167 | 12 months | 2,654 | 18.0% | Studio: 38 sales, median 1,200,000 AED; 1 bedroom: 101 sales, median 1,750,000 AED; 2 bedrooms: 28 sales, median 2,745,000 AED | |
| Business Park | Active | 151 | 12 months | 3,139 | 100.0% | 1 bedroom: 44 sales, median 2,365,500 AED; 2 bedrooms: 79 sales, median 4,579,540 AED; 3 bedrooms: 27 sales, median 6,313,000 AED | |
| Business Bay | Finished | 125 | 12 months | 2,442 | 100.0% | 1 bedroom: 85 sales, median 1,456,000 AED; 2 bedrooms: 40 sales, median 2,150,000 AED | |
| Business Bay | Finished | 78 | 12 months | 2,580 | 58.0% | Studio: 24 sales, median 1,130,000 AED; 1 bedroom: 30 sales, median 1,655,000 AED; 2 bedrooms: 24 sales, median 2,350,000 AED | |
| Business Bay | Finished | 76 | 12 months | 2,784 | 0.0% | Studio: 20 sales, median 1,250,000 AED; 1 bedroom: 28 sales, median 1,810,000 AED; 2 bedrooms: 23 sales, median 2,630,000 AED; 3 bedrooms: 5 sales, median 4,300,000 AED | |
| Business Park | Active | 61 | 12 months | 3,181 | 100.0% | 1 bedroom: 20 sales, median 2,447,000 AED; 2 bedrooms: 36 sales, median 2,928,000 AED; 3 bedrooms: 4 sales, median 6,293,500 AED | |
| Business Bay | Finished | 17 | 12 months | 2,621 | 0.0% | 1 bedroom: 7 sales, median 2,150,000 AED; 2 bedrooms: 4 sales, median 4,275,000 AED; 3 bedrooms: 4 sales, median 4,675,000 AED |
Source: Dubai Land Department; data through 22 Oct 2026. Home-size medians come from each building's home sales. A row needs a project-to-building link for this developer in the existing register. That building must have at least 10 home sales in its published price window. Sales and home-size samples cover the matched building, not necessarily units sold by this developer. They are not the developer’s complete sales ledger.
Questions people ask about Select Group
These answers explain the Select Group project records and the coverage of this dataset.
How many Select Group projects are covered by this dataset?
This page covers 8 projects with 4,764 homes. There are 6 finished projects and 2 under construction. Figures run to 22 Oct 2026.
Which projects has Select Group registered?
Projects include: Artistry One Residences. Artistry Two Residences. The Edge. Peninsula Four. Peninsula Three. The lists above show each project's status as of 22 Oct 2026.
Which communities appear in Select Group's project register?
Communities include: Business Park. Business Bay. These names come from the project register, as of 22 Oct 2026.
How long does Select Group take to build a project?
Its finished projects took a median 36 months to build. This runs from the registered start to finish.
Sources
Source update: 26 Oct 2026. Source for rents, yields and project records: Dubai Data (datadubai.ae), Continental Club Property, based on Dubai Land Department open data, data to 22 Oct 2026, licensed CC BY 4.0. Publisher contract sample, register data to 22 Oct 2026; the lease period is not stated. Publisher-reported gross yields use the publisher matched-segment sale-price denominator, not this page’s sale median; the matched-sale reporting period is not stated. Developers never pay to change these numbers.